combined with the tree, this sidewalk is impassable to wheelchairs, strollers, etc
sidoo kale waydiiyey...
S. Is the damage level high enough to be a hazard to citizens?
J. No
J. No
S. Is the panel is cracked or has a hole, if so: How deep is it?
J. Wax Jawaab ah lama Bixin
J. Wax Jawaab ah lama Bixin
S. How high is the panel is raised?
J. Wax Jawaab ah lama Bixin
J. Wax Jawaab ah lama Bixin
4 Faalladas
La qiray Jesse Moos (Isticmaale Diiwaangashan)
Hi Skrap,
Thank you for contacting the City of Somerville with this needed sidewalk repair at 35 Windsor road. I have created work order 269494 to have it fixed and to have it be ADA compliant. If you have any further questions or comments please either email the office at 311updates@somervillema.gov or call us directly at 617-666-3311.
Thank you,
Jesse Moos
Constituent Services
City of Somerville
www.somervillema.gov
www.facebook.com/311Somerville
www.twitter.com/311Somerville
Jesse Moos (Isticmaale Diiwaangashan)
Hi Skrap,
Just wanted to give you a little follow up, sidewalk repairs are done from May 1st through November 1st each year, meaning this will not be completed until next Summer. If you have any further questions or comments please either email the office at 311updates@somervillema.gov or call us directly at 617-666-3311.
Thank you,
Jesse Moos
Constituent Services
City of Somerville
www.somervillema.gov
www.facebook.com/311Somerville
www.twitter.com/311Somerville
skrap (Isticmaale Diiwaangashan)
La xidhay Heather (Isticmaale Diiwaangashan)
Good Afternoon,
This issue has been fixed. Thank You